Tasks - Pre-Requisites

Modified on Wed, 21 Oct at 2:34 PM

Introduction

About this guide

 

This guide explains how to configure the key prerequisites required before Tasks can be used: 

  • Task Statuses and Transitions
  • Task Types
  • Access Roles

 

Create Task Status and Transitions

Creating Task Statuses

 

To begin, create the task statuses. Go to Administration, open the Task tab, and then select Status:

 

 

 

 

Next, you can edit or add Statuses that apply to Tasks. To add one, click on ‘Add’ in the top right of the page:

 

 

Each Status needs a name, and a status type. Status types are based on the defaults provided by the system (Open, Under Review, Work in Progress, etc). 

 

 

Set Final to Yes for any status that represents the end of a task lifecycle, such as Closed or Complete.

 

Create the statuses that you require for this transition. Once all Statuses have been configured and saved, click on the ‘transitions’ tab marked below:

 

 

Creating a Task Transition

 

From the Transitions tab, you can edit the Status Lifecycle Transitions that apply to Tasks or create a new transition by selecting Add.

 

 

Each Transition needs a name, with a Type specified as "Task". Denote what the Initial (First) status should be in this Transition, and the Final (Last) status should be. Then, click on ‘Add’ to continue:

 

 

Configure each allowed status change, such as Open to Under Review, Under Review to Work in Progress, and Work in Progress to Closed.

 

 

You need to do this, otherwise you will not be able to change a Task's Status.

 

Scroll back up and click on ‘Save’ once finished.

 

Configuring Task Type 

Adding Task Types

 

To set up a task type, go to Administration > Task, then select Type as shown below:

 

 

You will then be able to view existing task types, or you can add a new type by clicking on ‘Add’.

 

When adding a new task type, complete the required fields shown below:

 

  • Type – For example, Garden Waste or Potholes.

 

  • Code - If one is not inputted, this will be automatically generated.

 

  • Transition – Select as previously configured.

 

  • Catalogue and Form - Select this only if the task type will be used for task forms.


  • Layout - Select this only if a specific layout is required; otherwise, the default layout will be assigned.

 

 

After adding the task type, you will then find additional options show which you can add if required. 

 

  • Subject - The subject of the task which the worker will view to identify the job.

 

  • Action - The action required to complete the task.

 

  • Owner - Main user who is responsible for the task. When a task is created, this user will be the owner of the task by default.

 

  • Collaborator - Additional users who will be involved with this task.

 

 

 

Access Roles (Task Type)

Allowing Users to See Tasks

Task types must be assigned through Access Roles. To configure this, navigate to Administration > Access > Access Control.


Within this section, you can either select an existing Access Role or create a new one by clicking Add New Role.


When creating or editing an Access Role, locate the Task section. Use the dropdown menu to select the Task Type that the role should have permission to view. For example, Dog Fouling is selected here:



Users assigned to this Access Role can view the selected Task Types, provided the task has also been assigned to them.

Was this article helpful?

That’s Great!

Thank you for your feedback

Sorry! We couldn't be helpful

Thank you for your feedback

Let us know how can we improve this article!

Select at least one of the reasons
CAPTCHA verification is required.

Feedback sent

We appreciate your effort and will try to fix the article